Judge Reviews Proposed N.Y. Hazardous Waste Landfill Expansion

The state is considering whether it will allow a 44-acre cell to once again receive industrial and hazardous waste.

Arlene Karidis, Freelance writer

July 31, 2018

3 Min Read
Judge Reviews Proposed N.Y. Hazardous Waste Landfill Expansion

The subject of a long-debated proposed expansion at a closed hazardous waste facility in Niagara County, N.Y., has come before a judge again.

Still, it could be some time before the state decides whether to allow CWM Chemical Services, owned by Waste Management, to dig a 44-acre cell to once again receive materials from brownfields, environmental cleanups and industrial and hazardous waste generators. The landfill reached capacity and closed in November 2015.

The latest activity was an “issues conference,” held mid-July to determine whether two topics of contention will be subject to an adjudicatory hearing: a drafted air and a drafted water discharge permit that were issued by the Department of Environmental Conservation (DEC).

The judge has yet to determine if concerns around the permits will go to hearing, and if so, which specific, related issues will be adjudicated. Other issues already have been identified for adjudication, such as transportation; groundwater considerations; and impacts of the project on property values, economic development and marketability of agricultural products.

Multiple community parties with grievances participated in the conference, including Lewiston-Porter Central School District, Residents for Responsible Government and Niagara County Farm Bureau, the villages of Lewiston and Youngstown, resident Amy Witryol, Tuscarora Nation and the Buffalo Niagara Waterkeeper.

Among comments that came out of the proceeding, reported in the Niagara Gazette, were those of Waterkeeper attorney Margaux Valenti and Tuscarora attorney Jenna Macaulay.

Tuscarora opposes the additional discharge of contaminated water that Valenti says would carry harmful chemicals to the Niagara River ecosystem. 

Macaulay argues that digging the cell would result in potentially toxic dust that would impact the nation’s territory and says the nation has a zero water pollution acceptance level.

CWM attorneys assert the company would meet requirements to justify the permits and there would be no resulting public health risks.

Lewiston Town Supervisor Steve Broderick explains to Waste360 why his town is trying to stop the expansion.

“Over 99 percent of truck traffic that hauls hazardous waste goes through Lewiston,” he says. “A lot of citizens here are against toxic waste, and the town’s involvement came out of the public’s concerns. We would like to see no more toxic waste in our county.”

Duffy Johnston, supervisor of the town of Porter, says as host of the landfill, Porter is bound by an agreement prohibiting him from speaking on the proposed expansion.

Niagara County Legislature Spokesperson Christian Peck would comment only as far as to say: “Niagara County has been actively engaged with the DEC via expert legal counsel throughout the review process for CWM's proposal. We are trusting in our counsel to ensure our county's interests are protected by this process and in the DEC to exercise prudence.”

“This has been a long, arduous process with a significant amount of scrutiny given to technical details on all aspects of the permit,” says Lori Caso, a Waste Management spokeswoman. “We are confident that in the near future, we will be able to once again service our customers who rely on us for safe disposal.”

Moving forward, there could be more steps before a final decision is made. Any issues ruling is subject to appeals to the siting board and the office of the DEC commissioner. Then, pending outcomes, the siting board will approve or reject a certificate for expansion. The DEC commissioner ultimately decides.

The Niagara County landfill, owned by Waste Management since 1984, is the only hazardous waste site in New York State and is one of five Waste Management facilities across the U.S. that specializes in industrial and hazardous waste treatment.

Without a new hazardous waste operation here, Caso says materials would go to a competitor in Michigan or to the nearest waste management facility in Alabama, significantly adding to transportation costs and emissions.

About the Author

Arlene Karidis

Freelance writer, Waste360

Arlene Karidis has 30 years’ cumulative experience reporting on health and environmental topics for B2B and consumer publications of a global, national and/or regional reach, including Waste360, Washington Post, The Atlantic, Huffington Post, Baltimore Sun and lifestyle and parenting magazines. In between her assignments, Arlene does yoga, Pilates, takes long walks, and works her body in other ways that won’t bang up her somewhat challenged knees; drinks wine;  hangs with her family and other good friends and on really slow weekends, entertains herself watching her cat get happy on catnip and play with new toys.

Stay in the Know - Subscribe to Our Newsletters
Join a network of more than 90,000 waste and recycling industry professionals. Get the latest news and insights straight to your inbox. Free.

You May Also Like